Calculation basis & assumptions
This is an indicative client payment forecast, excluding tax, inflation, variations, finance charges and contractor costs. It does not calculate a contractor funding gap. The S-curve uses normalized bell-shaped monthly work weights; front/back profiles use declining/increasing linear weights. Custom profiles are redistributed proportionally across scenario durations.
Retention is deducted at the selected percentage of gross work value on every work certificate. Advance recovery is proportional to gross work, with full recovery by completion. Retention release dates are modeled assumptions, not contract interpretations. Duration changes redistribute the same scope and price; they do not add delay costs. Payment lag uses whole monthly buckets. The commencement month includes the advance and, with zero lag, the first work payment. Total payments including releases reconcile to contract value.